About 276 of roughly 6,650 tariff lines are under import control, mostly specific goods such as certain chemicals, fuels, tyres and arms rather than machinery.
New versus used machinery
| Situation | ITAC import permit? | Notes |
|---|---|---|
| New machine or line, standard production machinery | Usually not | Check that the tariff line is not under import control |
| Used or second-hand machine | Yes | Apply before shipment |
| Refurbished or rebuilt machine | Treat as used | Ask ITAC if in doubt |
| Machine containing controlled items | Possibly | For example equipment with radioactive sources |
| Ex-demonstration or display machine | Treat as used | Ask ITAC before shipping |
The key word is "used". ITAC's position is that an import permit is required for the importation of all used or second-hand goods, whatever their age or condition.
Which goods are under import control?
ITAC lists the goods most frequently controlled. Among them:
- Radioactive chemical elements.
- New pneumatic tyres.
- Chemicals listed in the 1988 UN Convention on narcotic drugs and precursors.
- Gambling devices.
- Fossil fuels.
- Arms and ammunition.
- Used goods, including electronic equipment, medical equipment, aircraft, and waste and scrap.
ITAC puts the total at about 276 tariff lines out of roughly 6,650. For a new production line, the practical question is usually whether anything in it is used, and whether any part falls into one of these groups.
How to apply for an ITAC permit
- Confirm the tariff heading of the equipment with your clearing agent.
- Download the application form from ITAC's application forms page.
- Prepare the supporting documents: pro-forma invoice, description and photographs of the used equipment, age and condition, and the reason for importing.
- Submit the application to the responsible ITAC official, by email or at ITAC's office, before the goods are shipped.
- Wait for the permit: ITAC's average turnaround is three to five working days, longer when another department must supply documents.
- Give the permit to your clearing agent so it can be presented with the customs declaration.
Some applications need supporting documents from other bodies, such as the environment department, energy, agriculture, the NRCS or the police, depending on the goods.
What a permit costs and how long it takes
| Item | Typical position |
|---|---|
| ITAC permit fee | None; ITAC does not charge for import permits |
| Processing time | About three to five working days on average |
| When to apply | Before the goods are shipped |
| Who applies | The importer, or an agent on its behalf |
Plan the application into your shipping schedule; a used machine that arrives without a permit can be held at the port while one is obtained, and storage charges run in the meantime.
SARS customs registration comes first
Whatever you import, the importer must be registered with SARS as a customs client. Registration, licensing and accreditation are handled through SARS's customs registration process; your clearing agent declares the goods under your registration. Register before the first shipment.
Documents for a machinery import
- SARS customs client registration of the importer.
- Commercial invoice and packing list with technical descriptions.
- Bill of lading.
- ITAC import permit, for used or controlled goods.
- Certificate of origin, where a preferential duty rate is claimed.
- Technical data sheets to support the tariff classification.
Choosing who handles the permit
If you use a clearing agent or freight forwarder, check that they:
- Ask whether any item is used before the booking is made.
- Know which tariff lines are under import control.
- Prepare or check the ITAC application before shipment.
- Give you a written estimate of duty, VAT and port charges.
- Have cleared machinery, not only consumer goods, before.
Common mistakes
- Assuming a "nearly new" machine is new. If it has been used, it needs a permit.
- Applying after the goods sail. The permit should be in place before shipment.
- Not registering with SARS. A shipment cannot be cleared without the importer's registration.
- Missing controlled components. Some equipment contains items that are themselves controlled.
- Ignoring duty while focusing on the permit. A permit does not change the duty; check headings separately with our duty rates table.
Other approvals a machinery import can meet
An ITAC permit is not the only approval that can apply to an equipment import. Check these before the goods ship:
- Pressure equipment. Boilers, pressure vessels and some refrigeration systems fall under the Pressure Equipment Regulations under the Occupational Health and Safety Act; they need design verification and registration, and inspection before use.
- Electrical products for sale. Some electrical and electronic products sold in South Africa need a Letter of Authority from the NRCS. Production machinery for your own use usually does not, but check any electrical items you will resell.
- Radioactive sources. Some level gauges and inspection devices contain radioactive sources, which need a licence from the radiation control authority as well as ITAC control.
- Wooden packaging. Crates and pallets should carry ISPM 15 treatment marks to avoid inspection delays.
A typical timeline for a used machine
| Step | Typical timing |
|---|---|
| Confirm heading and permit need with clearing agent | Before you pay for the machine |
| Prepare and submit ITAC application | A few days |
| ITAC processing | About three to five working days on average |
| Book freight once the permit is issued | Then ship |
| Sea transit China to Durban | About 22–30 days |
| Clearance with permit presented | Days, if documents are complete |
Starting the permit after the vessel sails is the most common way to add weeks of port storage to a used-machine purchase.
The legal basis
Import control is administered by ITAC under the International Trade Administration Act 71 of 2002, read with the Customs and Excise Act 91 of 1964, under which SARS clears goods. South Africa values imports on the FOB price for customs purposes, and import VAT of 15% is charged on the customs value plus 10% plus duty.
Where CISH fits
On CISH turnkey projects we supply new lines from audited factories in China, check every item's heading and permit status before shipment, and ship, clear, install and commission the line. If a project includes refurbished equipment, we apply for the ITAC permit before it ships. If you are importing a used machine yourself, follow the steps above and line up the permit before you pay for freight.
For used machines in detail, see importing second-hand machinery into South Africa.
Frequently asked questions
Do I need an import permit for machinery in South Africa?
Not for new production machinery in general. Used or second-hand machinery needs an ITAC import permit, and a small number of controlled tariff lines need permits even when new.
How long does an ITAC permit take?
ITAC's average turnaround is three to five working days, longer if another department must provide supporting documents.
How much does an ITAC import permit cost?
ITAC does not charge a fee for import permits.
When should I apply for an import permit?
Before the goods are shipped. A used machine that arrives without a permit can be held at the port.
What goods are under import control in South Africa?
About 276 of roughly 6,650 tariff lines, including radioactive elements, new pneumatic tyres, certain chemicals, gambling devices, fossil fuels, arms and ammunition, and used goods such as electronic and medical equipment.
Is an import licence the same as an import permit?
People use the words interchangeably. In South Africa, the ITAC document for controlled or used goods is an import permit, while registration with SARS as a customs client is what allows you to import at all. A business importing new, uncontrolled machinery needs the SARS registration but not an ITAC permit.
Can I apply for the permit after the machine arrives?
You should not plan to. ITAC expects the application before shipment, and goods that arrive without a required permit can be held, with storage costs, until the position is resolved.
Do I need to register with SARS to import?
Yes. Every importer must be registered as a customs client with SARS before goods can be cleared.
Does CISH handle import permits?
On our turnkey projects, yes. We check permit requirements for every item before it ships.