Taking eThekwini (Durban) as the worked example: under its Sewage Disposal By-law, 2016, no one may discharge trade effluent without permission; you apply as the municipality requires and pay the prescribed fee; permission is granted only if the sewers and treatment works have capacity; and the effluent must meet the limits in the by-law's schedules, such as temperature below 44 °C, pH between 6 and 10 (6.5 and 10 for smaller works), vegetable oils up to 250 mg/ℓ and sugars and starch up to 1,000 mg/ℓ (500 for smaller works). Chemical oxygen demand (COD) is not capped but charged: permit holders pay extra for effluent stronger than standard domestic effluent. Cape Town's by-law similarly requires owners of new or acquired trade premises to apply in writing and to pass effluent containing fats, oils and grease through a treatment facility.

Regulations change. Confirm the current requirement with the authority named in each section before you commit money.

Who needs a trade effluent permit

Any business that discharges wastewater other than ordinary domestic sewage, from toilets, basins and kitchens used by staff, into the municipal sewer. For food factories that includes washing water from raw materials, cooking and blanching water, cleaning and CIP solutions, spilt product, brine and whey. If you plan to discharge to a river, the ground or the sea instead, other rules under the National Water Act apply and the Department of Water and Sanitation is involved.

Authority: your municipality's water and sanitation department (Department of Water and Sanitation for discharges outside the sewer).

How the permission works: eThekwini example

Under section 25 of the eThekwini Sewage Disposal By-law, 2016:

  1. No discharge without permission. Trade effluent may only be discharged in terms of permission granted under the by-law, its conditions and any standards the authorised official sets.
  2. Application and fee. You apply as the authorised official requires and pay the prescribed fee.
  3. Capacity. Permission is granted if there is enough capacity in the system to convey, treat and lawfully dispose of the extra effluent.
  4. Standards. Effluent must meet Schedules A and B of the by-law.
  5. Conditions. The official may set the duration of the permission, add conditions, or relax standards in some circumstances, considering whether your plant uses the best available technology and minimises waste.
  6. Changes. You need written permission before changing the composition of your effluent.

Authority: eThekwini Water and Sanitation.

Discharge limits: eThekwini Schedule A

ParameterLarger works (over 25 Mℓ/day)Smaller works
TemperatureBelow 44 °CBelow 44 °C
pH6–106.5–10
Mineral oils50 mg/ℓ50 mg/ℓ
Vegetable oils and fats250 mg/ℓ250 mg/ℓ
Sugars and starch1,000 mg/ℓ500 mg/ℓ
Sulphates250 mg/ℓ250 mg/ℓ
Chlorides1,000 mg/ℓ500 mg/ℓ
Suspended solids2,000 mg/ℓ1,000 mg/ℓ
Conductivity400 mS/m400 mS/m
COD and settleable solidsCharged, not limitedCharged, not limited

Which column applies depends on the treatment works your sewer drains to. Other metros publish their own limits; check your municipality's by-law and permit conditions. Cape Town's by-law, for example, prohibits discharging liquids hotter than 40 °C or with a pH below 5.5 or above 12 without the City's consent.

Authority: your municipality.

Charges: you pay for strength as well as volume

Municipalities charge for trade effluent by volume and, in many cases, by strength. Under the eThekwini by-law, a permit holder discharging more than a prescribed minimum volume a month pays at least the charge for standard domestic effluent per kilolitre, plus an additional charge for high-strength effluent, effluent stronger than standard domestic effluent, calculated by the municipality's prescribed formula. COD is usually the main driver for food factories: sugars, starches, milk solids, fats and spilt product all raise it. Tariffs change each year; ask your municipality for the current formula and rates and estimate the bill for your plant before you build.

Authority: your municipality's tariff schedule.

What the municipality can require of you

Under the eThekwini by-law, the authorised official may require, at your cost:

  • Pre-treatment so that effluent meets the standards before it reaches the sewer.
  • Equalising tanks, valves, pumps and meters to control the rate and time of discharge.
  • A separate drain for trade effluent, apart from domestic sewage, with a manhole or stop-valve.
  • Protection against spills, such as level or overflow detection, standby equipment and overflow catchpits.
  • Calibration of meters by an independent authority.
  • Analysis of your effluent as often as prescribed, with returns to the municipality.
  • Bunds around liquid containers, holding at least the volume of the largest container, and roofs to keep stormwater out.

A duly qualified sampler may take samples at any time. Cape Town's by-law likewise requires effluent likely to contain grease, oil, fat or suspended solids to pass through a suitable treatment facility before it enters the sewer.

If you exceed the limits

If you discharge effluent that does not comply with your permit, the eThekwini by-law requires you to notify the authorised official within 12 hours, with the reasons. The municipality may withdraw permission after 14 days' written notice if you fail to comply or to pay, close or seal your sewer connection, and refuse further effluent until you show it will comply. Where a discharge could seriously damage the sewer system or the environment, the connection can be sealed immediately. Without a sewer connection, a food factory cannot run.

Authority: your municipality.

Pre-treatment for food factories

Wastewater issueTypical pre-treatment
Fats, oils and greaseGrease traps, dissolved air flotation
Solids and peelScreens, settling tanks
High or low pH from CIPNeutralisation tank with dosing
Uneven flowsEqualisation tank
High CODReduce at source; biological pre-treatment for large loads
Hot waterCooling or heat recovery before discharge

The cheapest effluent is the one you never make: catch product and solids before they reach the drain, dry-clean before washing, recover CIP solutions, and fix leaks. Budget pre-treatment with the line, not after the first municipal letter; our guide to the cost of setting up a small factory shows where it sits in a project.

The application: what to prepare

  • Site and drainage plans showing trade and domestic drains, sampling points and pre-treatment.
  • Process description: products, volumes, cleaning methods and chemicals.
  • Expected effluent volumes and quality: flow per day, peak flow, COD, pH, fats and solids.
  • Pre-treatment design and how it will be operated.
  • Laboratory analysis where the plant already runs.

For a new factory, apply with your building plans: Cape Town's by-law requires owners building or acquiring trade premises to apply in writing for permission to discharge industrial effluent.

Worked example: a dairy in Durban

A dairy in Pinetown makes milk, maas and yoghurt and plans to double output. Its effluent includes milk residues and CIP caustic and acid. Before expanding, it installs a screen, a grease trap, an equalisation tank and a pH correction tank with dosing, separates trade and domestic drains with a sampling point, and applies to the municipality for revised permission. It recovers rinse milk and cleaning solutions to cut COD and the strength charge. The figures and names are illustrative.

Common mistakes

  • Starting production without permission to discharge.
  • No equalisation, so peaks from CIP break the pH limits.
  • Ignoring strength charges in the business plan.
  • No grease trap or one that is never emptied.
  • Changing products without telling the municipality.

Where CISH fits

CISH supplies, installs and commissions food processing lines together with the pre-treatment they need, screens, grease traps, equalisation and neutralisation, from audited factories in China, sized to your products and effluent. We design the line to reduce wastewater at source and provide the process information your application needs. The permit and ongoing compliance stay with you as the discharger.

Frequently asked questions

Does a food factory need a trade effluent permit?

Usually yes, if it discharges process wastewater to the municipal sewer; the municipality's by-law sets the rules.

What limits apply to food factory effluent?

Each municipality sets its own; eThekwini, for example, sets pH 6–10, temperature below 44 °C and vegetable oils up to 250 mg/ℓ for larger works.

How are trade effluent charges calculated?

By volume and, in many municipalities, by strength such as COD, using a formula in the tariff schedule.

What happens if I exceed the limits?

In eThekwini you must report within 12 hours; repeated non-compliance can lead to withdrawal of permission and sealing of the connection.

What pre-treatment do food factories need?

Commonly screens, grease traps, equalisation and pH correction, depending on the products.

Does CISH supply pre-treatment with food lines?

Yes, sized with the line, with commissioning and training.