But some processes are listed at much smaller sizes, including wood drying and burning above 10 tonnes a month, rendering or drying of animal matter not intended for human consumption above 1 tonne of raw material a day, and charcoal production above 20 tonnes. Licences are issued by the metropolitan or district municipality, or the province where it has taken over the function. Boilers below the listing threshold can still face emission standards as controlled emitters.

Regulations change. Confirm the current requirement with the authority named in each section before you commit money.

How the AEL system works

ElementWhat it means
Listed activityA process the Minister has listed because it can significantly affect air quality
ThresholdThe size above which the activity is listed, such as heat input or tonnes a month
Atmospheric emission licenceRequired before a listed activity is carried out
Minimum emission standardsLimits on particulates, sulphur dioxide, nitrogen oxides and other pollutants for each listed activity
Licensing authorityMetropolitan or district municipality, or the province where it has taken over the function or the activity crosses boundaries
Controlled emitterAppliances, such as small boilers, that must meet emission standards without being listed activities

Which factory processes are listed?

The thresholds below are from GN 893 of 2013. The notice has been amended several times, so check the current consolidated version and any newer amendments.

ProcessSubcategoryListed above
Boilers and furnaces burning coal or other solid fuel1.1Design capacity of 50 MW heat input per unit
Boilers burning liquid fuel, such as diesel or heavy fuel oil1.250 MW heat input per unit
Boilers burning solid biomass, such as wood or bagasse1.350 MW heat input per unit
Gas-fired installations1.450 MW heat input per unit
Reciprocating engines, such as large generator sets1.510 MW heat input
Char and charcoal production3.4Production of more than 20 tons of char and charcoal
Drying of mineral solids with dedicated combustion5.2More than 100 tons a month of product
Wood burning, drying and manufactured wood products9.5More than 10 tons a month
Rendering, cooking, drying or protein concentrating of animal matter not for human consumptionCategory 10More than 1 ton of raw material a day

Other categories cover large industries such as cement, metals, chemicals, petroleum, pulp and paper, and waste incineration.

What this means for common production lines

  • Food factories with steam boilers. A boiler for a bakery, dairy, juice or snack line is usually far below 50 MW heat input, so it is not a listed activity. It may still be a controlled emitter: small boilers of 10–50 MW heat input were declared controlled emitters in 2013, with their own emission standards.
  • Charcoal and briquette plants. Carbonisation of wood or biomass into charcoal is listed above the subcategory 3.4 threshold, and drying wood with external heat is listed above 10 tonnes a month. A charcoal briquetting plant often needs an AEL; a plant briquetting bought-in charcoal dust without carbonising may not.
  • Pallet plants with heat treatment. ISPM-15 heat treatment dries wood with external heat; check whether your volume crosses the subcategory 9.5 threshold.
  • Rendering and pet food from by-products. Cooking and drying animal matter not intended for human consumption is listed above 1 tonne of raw material a day, with an extra requirement to manage odours.
  • Standby generators. Most factory generator sets are far below 10 MW heat input; very large installations should be checked.
  • Dryers for food or minerals. Dryers for food are not in subcategory 5.2, which covers mineral solids; but the fuel installation behind any dryer should be checked against Category 1.

Your air quality consultant should confirm the position for your plant against the current notice.

Who issues the licence

Metropolitan and district municipalities are the licensing authorities. Where a municipality has delegated the function to the province, or where the activity crosses municipal boundaries, the province is the licensing authority. Start with the air quality officer at your metro or district municipality.

How to apply, step by step

  1. Screen the plant. List every fuel-burning appliance with its design heat input, every dryer, kiln and furnace, and the tonnages processed.
  2. Compare with the listed activities and thresholds in the current notice.
  3. Check whether an environmental impact assessment is also triggered. Where the activity also needs environmental authorisation under NEMA, the processes run together.
  4. Appoint an air quality consultant if the activity is listed; most applicants do.
  5. Prepare the application: process description, emission sources, fuel use, abatement equipment, stack heights, an atmospheric impact assessment where required, and public participation.
  6. Submit to the licensing authority, which may ask for more information, investigate the likely effect on air quality, invite comments and give you a chance to respond to objections.
  7. Receive a provisional AEL, commission the plant, and demonstrate compliance with the emission standards before the full licence is issued.
  8. Comply and report: measurements, records and annual reporting as the licence requires.

Timelines and fees differ between licensing authorities. Allow months, not weeks, and start before the equipment is ordered.

Design choices that reduce the burden

  • Fuel choice. Gas or electricity instead of coal or heavy fuel oil reduces emissions and monitoring.
  • Boiler sizing. Size steam boilers to the real demand, with heat recovery.
  • Abatement equipment. Cyclones, bag filters and scrubbers built into the line design.
  • Stack design. Height and sampling ports that meet the standards from day one.
  • Odour control for rendering and some food by-product processes.

Common mistakes

  • Assuming "small" means exempt. Some processes are listed at a few tonnes a month.
  • Ordering a coal boiler before checking emission standards.
  • No sampling ports in the stack.
  • Forgetting the generator on very large standby installations.
  • Starting operation on a provisional licence without meeting its conditions.

Where CISH fits

CISH supplies complete production lines from audited factories in China. For any line with a boiler, dryer, kiln or furnace, we provide the design heat input, fuel type and consumption, burner data, flue gas figures from the manufacturer and stack details your consultant needs, and we can include abatement equipment in the line. Licence applications are made by the plant owner, usually through an air quality consultant.

Charcoal makers should read how to start a charcoal business in South Africa alongside this page.

Frequently asked questions

What is an atmospheric emission licence?

A licence under the Air Quality Act that is required before anyone carries out a listed activity, a process that can significantly affect air quality.

Does my factory boiler need an AEL?

Usually not. Fuel-burning installations are listed from 50 MW heat input per unit. Smaller boilers can still be controlled emitters with emission standards.

Does a charcoal plant need an AEL?

Often yes. Char and charcoal production is listed above 20 tons, and wood drying with external heat above 10 tons a month. Check the current notice for your volumes.

Who issues atmospheric emission licences?

Metropolitan and district municipalities, or the province where the function is delegated or the activity crosses municipal boundaries.

How long does an AEL take?

It varies by licensing authority and by whether an environmental impact assessment is also needed. Allow several months.

Can I operate while my AEL is being processed?

Not a listed activity. You need a provisional licence first, and must meet its conditions during commissioning.

Does CISH apply for AELs?

No. We supply the lines and the technical data; the plant owner applies, usually through an air quality consultant.