Larger hazardous-waste recycling and very large recovery operations are Category B, needing a full scoping and environmental impact assessment. Sorting, shredding, grinding, crushing, screening or baling general waste at a facility of 1,000 m² or more is Category C, which means complying with national norms and standards rather than holding a licence. Regulations change. Confirm the current requirement with the authority named in each section before you commit money. CISH supplies, installs and commissions complete recycling lines and can share the plant layout and area figures your environmental practitioner needs.
How the categories work
GN 921 lists waste management activities in three categories, each with a different process:
| Category | What you must do | Who decides |
|---|---|---|
| Category A | Conduct a basic assessment under the NEMA EIA Regulations as part of a waste management licence application | The licensing authority, usually the provincial environmental department |
| Category B | Conduct a scoping and environmental impact reporting process as part of a licence application | The licensing authority, often national for hazardous waste |
| Category C | Comply with the relevant national norms and standards | You comply and register; the authority inspects |
A licence takes longer and costs more than compliance with norms and standards. That is why the thresholds matter so much at the planning stage.
Thresholds that affect recycling plants
| Activity under GN 921 | Threshold | Category |
|---|---|---|
| Recycling of general waste | Facility with more than 500 m² of operational area (excluding recycling integral to a manufacturing process on the same premises) | A |
| Recycling of hazardous waste | More than 500 kg but less than 1 tonne a day, monthly average | A |
| Recovery of waste, including refining, utilisation or co-processing | More than 10 but less than 100 tonnes of general waste a day | A |
| Reuse or recycling of hazardous waste | More than 1 tonne a day | B |
| Recovery of waste | More than 100 tonnes of general waste a day | B |
| Storage of general waste | Capacity to store more than 100 m³ at any one time | C |
| Sorting, shredding, grinding, crushing, screening or baling of general waste | Facility with 1,000 m² or more of operational area | C |
The sorting and baling activity moved from Category A to Category C in 2017 (GN 1094 of 2017), so many baling yards now follow norms and standards instead of needing a licence.
Worked examples
| Plant | Likely category | Why |
|---|---|---|
| Small baling yard of 600 m², sorting and baling cardboard and PET | Possibly none, or Category C for storage above 100 m³ | Below 1,000 m² for sorting and baling; check storage capacity |
| Baling yard of 2,000 m² | Category C | Sorting and baling at 1,000 m² or more |
| PET washing and pelletising plant of 1,500 m² | Category A | Recycling general waste above 500 m² |
| Converter recycling its own production scrap inside its factory | Usually excluded | Recycling integral to its own manufacturing process |
| Plant recycling solvent or oil (hazardous) above 1 t/day | Category B | Hazardous waste above 1 tonne a day |
These are illustrations. The authority decides how your activity is classified, so ask before you commit.
Steps to a waste management licence (Category A)
- Define the activity: materials, tonnes per day, processes, operational area and storage.
- Pre-application meeting with the licensing authority to confirm the category and requirements.
- Appoint an environmental assessment practitioner to run the basic assessment.
- Public participation: notices, comment periods and responses.
- Specialist studies where required, such as traffic, noise, stormwater or groundwater.
- Submit the basic assessment report and licence application.
- Decision and licence conditions, which then govern operations, monitoring and reporting.
Other approvals usually run alongside: municipal zoning and building plans, an atmospheric emission licence if there are listed emissions, and water use authorisation if you abstract or discharge water.
Complying with norms and standards (Category C)
For Category C activities, there is no licence, but you must comply with the relevant norms and standards, which typically cover:
- Registration with the competent authority before you start.
- Site design: hard surfaces, drainage and stormwater control, fencing and access control.
- Operations: housekeeping, fire prevention, dust and noise control, and storage limits.
- Records and reporting: incoming and outgoing tonnages.
- Training of staff and emergency procedures.
Read the norms and standards that apply to your activity, such as those for storage of waste or for sorting, shredding, grinding, crushing, screening or baling, and design the site around them.
How the licence affects plant design
| Licence or standard issue | Design response |
|---|---|
| Operational area thresholds | Plan the layout area deliberately; it decides the category |
| Storage limits | Size bale and raw material stores to the allowed volume |
| Stormwater and spills | Bunded areas, drainage and collection |
| Wash water | Treatment and recirculation on washing lines |
| Dust, noise and odour | Enclosures, filters and operating hours |
| Fire risk | Separation of stockpiles, firebreaks and fire protection |
Other approvals to run alongside
A waste licence or registration rarely stands alone. Most recycling plants also need municipal zoning that allows the use, approved building plans, and a business licence where the municipality requires one. Washing lines need water and an effluent route, which can mean a trade effluent permit from the municipality. Plants with listed emissions may need an atmospheric emission licence. Plan these approvals together, because the same site information feeds all of them.
Common mistakes
- Signing a lease before checking the category.
- Measuring only the building. Operational area can include outdoor storage and handling.
- Assuming baling and washing are the same category. Baling may be Category C; washing and pelletising may be Category A.
- Ignoring hazardous waste. Thresholds are much lower.
- Starting operations before the licence or registration is in place.
Where CISH fits
CISH supplies, installs and commissions complete recycling lines from audited factories in China, and provides the plant layout, areas, process descriptions, water and power figures your environmental assessment practitioner needs for the licence or registration. The licence is applied for in your company's name.
Frequently asked questions
Do I need a waste management licence to recycle plastic?
If you recycle general waste at a facility with more than 500 m² of operational area, it is a Category A activity under GN 921 of 2013, needing a basic assessment and a waste management licence. Recycling integral to your own manufacturing process on the same premises is excluded.
Does a baling yard need a licence?
Sorting, shredding, grinding, crushing, screening or baling of general waste at a facility of 1,000 m² or more is a Category C activity, which requires compliance with national norms and standards rather than a licence.
What is the difference between Category A and B?
Category A needs a basic assessment as part of the licence application; Category B needs a full scoping and environmental impact reporting process.
Who issues waste management licences?
Usually the provincial environmental department, with national authorities responsible for some activities, such as many involving hazardous waste. Confirm with the authority for your site.
Can I start operating while the licence is processed?
No. Listed activities may not start until the licence is issued or, for Category C, until you comply with the norms and standards.
Does storing recyclables need approval?
Storing more than 100 m³ of general waste at any one time is a Category C activity that must follow the norms and standards for storage of waste.
Do I need other approvals besides the waste licence?
Usually yes: municipal zoning and building plans, a trade effluent permit if you discharge waste water, and an atmospheric emission licence if the plant has listed emissions.