Registration is done on the department's water use registration system, and licence applications go through the electronic e-WULAAS system. The 2017 water use licence regulations say the application, consideration and decision should be completed within 300 days of submission. Regulations change. Confirm the current requirement with the authority named in each section before you commit money. CISH supplies, installs and commissions complete production lines, including water treatment, and provides the water volumes your application needs.
Why a borehole needs authorisation
The National Water Act treats water as a national resource held in trust by the state. Section 21 lists the water uses that are controlled, including taking water from a water resource, storing water, and discharging waste water. Taking groundwater from a borehole is one of them. Ownership of the land does not give an automatic right to take unlimited water from beneath it.
Three routes: Schedule 1, general authorisation or licence
| Route | When it applies | What you do |
|---|---|---|
| Schedule 1 | Small uses, mainly reasonable domestic use, as set out in the Act | No licence; stay within the Schedule 1 limits |
| General authorisation | Uses within the volumes and areas set in a published general authorisation | Register the use with the Department of Water and Sanitation and follow the conditions |
| Water use licence | Uses above general authorisation limits, or in areas where they do not apply | Apply for a licence through e-WULAAS |
Most factories that rely on a borehole for production take more than a domestic use. Whether a general authorisation covers you depends on the volume and on the catchment or aquifer where the borehole sits, because limits differ by area and some stressed areas are excluded. Ask the regional DWS office before drilling or buying a site for its borehole.
Registering a water use
Water uses under a general authorisation, and many existing uses, must be registered on the department's water use registration system. Registration records the user, the property, the source and the volumes. Keep records of the volumes you take, usually with a meter on the borehole.
Applying for a water use licence
| Step | What it involves |
|---|---|
| 1. Pre-application | Meet the regional DWS office to confirm the route and the information needed |
| 2. Hydrogeological study | A specialist assesses the aquifer, yield and impact on other users |
| 3. Application on e-WULAAS | Submit the application and supporting documents electronically |
| 4. Technical review | DWS reviews the application and may ask for more information |
| 5. Public participation | Where required, notify affected parties and respond to comments |
| 6. Decision | A licence with conditions, or a refusal with reasons; appeals are possible |
The Water Use Licence Application and Appeals Regulations, 2017 state that the application, consideration and decision should be completed within 300 days of submission, and that where a national electronic system is used for applications, all applicants must use it. Plan for the full period.
Other water uses a factory may have
| Water use | Example in a factory |
|---|---|
| Taking water | Borehole abstraction |
| Storing water | Large reservoirs or dams |
| Discharging waste water | Effluent to a river or land; discharges to a municipal sewer are usually controlled by municipal by-laws and trade effluent permits |
| Disposing of waste in a way that may affect water | Irrigation with effluent, evaporation ponds |
Each controlled use can need its own authorisation. A single integrated application can cover several uses.
Before you design a process around a borehole
- Test the yield with a pump test, so you know what the borehole can deliver over time.
- Test the water quality at an accredited laboratory, across seasons if possible.
- Check the authorisation route with the regional DWS office.
- Design treatment for the water quality and your product's needs.
- Plan for effluent, including reject water from reverse osmosis, which is often a large share of the intake.
- Install a meter and keep records from day one.
- Keep a backup supply, such as municipal water, in case yield drops.
How this affects a production line
A line's water demand drives the volume you apply for. Bottled water, beverages, dairy, food processing, washing lines in recycling and cooling systems can all use large volumes. Reverse osmosis systems reject part of the intake as concentrate, so the volume taken from the borehole is larger than the volume used in the product. Give the hydrogeologist and DWS realistic figures for intake, product water and effluent.
Working with a hydrogeologist
A registered hydrogeologist is usually the key adviser for a borehole application. They assess the aquifer, run or interpret pump tests, estimate a sustainable yield, look at the effect on neighbouring users and on surface water, and prepare the technical report the department reviews. Ask for experience in your area, because aquifers and departmental expectations differ from one catchment to another.
Give the hydrogeologist realistic figures from the start: daily and peak water demand, growth plans for the next few years, the treatment process and its reject volumes, and how effluent will leave the site. Applying for a volume that matches the plant's real needs, with a sensible margin, avoids a second application when you expand.
Common mistakes
- Drilling and pumping before checking the authorisation route.
- Assuming land ownership includes water rights.
- Applying for too little water, then needing a new application to expand.
- Ignoring reverse osmosis reject water in the water balance.
- No meter or records, which weakens your position at renewal or inspection.
- Forgetting effluent permits for discharges.
Where CISH fits
CISH supplies, installs and commissions complete production lines from audited factories in China, including water treatment. We provide the line's water demand, treatment design, reject volumes and effluent figures your hydrogeologist and DWS application need. The water use authorisation is applied for in your company's name.
Frequently asked questions
Do I need a licence for a borehole at my factory?
It depends on how much water you take and where. Small domestic uses fall under Schedule 1; some uses are covered by general authorisations that require registration; larger uses need a water use licence from the Department of Water and Sanitation.
How long does a water use licence take?
The 2017 regulations say the application, consideration and decision should be completed within 300 days of submission. Plan for the full period.
Where do I apply for a water use licence?
Through the Department of Water and Sanitation's electronic system, e-WULAAS, after a pre-application meeting with the regional office.
What is WARMS?
The department's water use registration system, used to register water uses such as those under general authorisations.
Does reverse osmosis reject water count?
Yes. The water you take from the borehole includes the reject, and discharging it can be a separate water use or need a municipal effluent permit.
Can I use borehole water for bottled water?
Yes, if the use is authorised and the water is treated and bottled under the bottled water regulations, such as water defined by origin.
Do I need a hydrogeologist?
For a licence application, usually yes. A registered hydrogeologist assesses the aquifer and yield, the effect on other users, and prepares the technical report the department reviews.
Can I expand my water use later?
You can apply to amend or for a new authorisation, but it takes time. Apply for a volume that matches realistic growth from the start.
What records should I keep for a borehole?
Meter readings of the volume taken, water quality test results, pump test reports, your registration or licence and its conditions, and any reports the authorisation requires. Good records support renewals and inspections.