What it usually does not include is just as important: the building and civil works, the main power supply and transformer, water and effluent connections, permits and licences in your name, raw materials and working capital are normally the client's, unless the contract says otherwise. Turnkey companies in South Africa range from engineering firms that design and build large plants, to equipment importers who add installation, to specialist line companies that supply complete lines from abroad. Choose by checking three running projects similar to yours, the people who will do the work, and a contract that ties payment to acceptance tests.

What "turnkey" should include

StageWhat the turnkey company does
Process designDefines the process, capacity, line layout and utilities for your product
Equipment specificationSelects and specifies every machine so they work together
Sourcing and manufactureBuys, builds or has the machines built; supervises quality
Factory acceptance testTests the machines at the factory on your product or a test material
Shipping and clearingPacking, freight, insurance, customs clearance, delivery to site
InstallationPositioning, levelling, mechanical and electrical connection
CommissioningRuns the line to the agreed output and quality on your materials
Training and handoverOperators, maintenance staff, manuals, drawings and spare parts
Warranty and supportDefects period, spares, remote and on-site support

What is usually excluded

Usually the client'sWhy
Land, building and civil worksSite-specific and often local contractors
Main power supply, transformer, generatorUtility applications and site electrical design
Water supply, effluent treatment, drainsMunicipal connections and permits
Licences and permitsMust be in the owner's name (COA, waste licence, emission licence, registrations)
Raw materials and packaging for trialsThe client's supply chain
Working capital and staffThe client's business

Some turnkey companies can manage these as well, for a fee. Whatever the split, put it in a scope matrix in the contract so there is no gap between what the company does and what you do.

Types of turnkey companies

  • Engineering and EPC firms design and build large plants, often with their own civil and electrical teams; strong for big projects, expensive for small ones.
  • Equipment importers and dealers sell machines and add installation; good for single machines, weaker on whole-line responsibility.
  • System integrators connect and automate machines from different makers; strong on controls and data.
  • Specialist line companies supply complete lines for specific industries from abroad and answer for output.

We do not name or rate companies. The difference that matters is who answers for the line's output once it is running.

How to check a turnkey company's track record

  1. Ask for three similar projects with names and contacts, and visit at least one that is running.
  2. Ask the reference what went wrong and how the company handled it.
  3. Meet the people who will design, commission and support your line, not only the sales team.
  4. Check the company on the CIPC register, its tax and VAT registration, and, if it imports, its customs registration.
  5. Ask for a sample scope matrix, FAT protocol and commissioning report from a previous project.
  6. Check how it supports lines after handover: spares stock, technicians, response times.

What to put in the contract

  • Scope matrix: who does what, including utilities and civil works.
  • Performance guarantee: output per hour, product quality, waste and uptime targets, measured over a defined test period.
  • Acceptance tests: FAT at the factory, site acceptance after commissioning, with the criteria in writing.
  • Payment milestones tied to FAT, shipment, installation and final acceptance, with a retention.
  • Delivery and commissioning dates, with what happens if they slip.
  • Warranty: period, coverage and response time.
  • Spares and training included.
  • Safety: machines guarded and compliant with the Driven Machinery Regulations.
  • Used equipment: if any, the ITAC permit is arranged before shipment.

Our guide to contract clauses has a fuller list.

Turnkey or buying machines yourself?

Turnkey companyBuying machines yourself
Price on the quoteHigherLower
Who designs the lineThe companyYou or each seller
Who answers for outputThe companyYou
Risk of gaps between machinesLowHigh
Your time and skills neededLessMuch more

The quote from a turnkey company includes design, coordination and risk that a buyer who buys direct carries alone. Our article does buying through CISH cost more works through that comparison.

Worked example: a juice line

A fruit farmer in the Western Cape wants to bottle juice. One option is to buy a pasteuriser, filler, capper and labeller from three sellers and hire a local electrician; another is a turnkey company that specifies the whole line, runs a FAT on water and juice concentrate in China, installs and commissions it, and guarantees 2,000 bottles an hour with agreed fill accuracy. The farmer builds the shed, the power supply and the effluent connection under a scope matrix, and pays the final 10% after a five-day site acceptance run. The steps are illustrative.

Common mistakes

  • No scope matrix: gaps nobody is responsible for.
  • Payment not tied to acceptance tests.
  • References that are not running.
  • No commissioning dates.
  • No spares plan after handover.

Your own team on a turnkey project

Even with a turnkey company, the client needs a project owner who can make decisions, a site or facilities person for the building and utilities, an electrician or electrical contractor for the main supply, a production manager who will run the line, and the future operators and maintenance staff for training. Name them at the start and give the turnkey company one point of contact on your side.

A typical timeline

A complete line usually follows this order: specification and quote; contract and deposit; manufacture; factory acceptance test; packing and pre-shipment check; shipping and clearing; delivery and installation; commissioning and training; site acceptance and handover. Building work and utilities run in parallel on your side and must be ready before the containers arrive. Ask for a dated plan and update it monthly with the turnkey company.

After handover

Agree how the line will be supported once it is running: the warranty period, a spare parts list with recommended stock, remote support, service visits and how fast a technician can be on site. The cost of a stopped line is usually far higher than the cost of good support.

Where CISH fits

CISH is a turnkey production line company. We specify complete lines for your product, supply them from audited factories in China, run the factory acceptance test, ship, clear and deliver them, install and commission them with output demonstrated, train your operators, and support the line after handover. Civil works, main power and permits are normally the client's, and we set them out in a scope matrix from the start.

For the safety rules a new line must meet, see factory registration and OHS Act rules for machinery.

Where an engineering firm fits instead, see when you need a process engineering company.

Frequently asked questions

What is a turnkey project company?

A company that delivers a working line or plant: design, equipment, installation, commissioning and training, answering for the result.

What does a turnkey contract usually exclude?

Usually land, buildings and civil works, main power and water connections, permits in the owner's name, raw materials and working capital.

How do I check a turnkey company?

Visit running projects similar to yours, meet the team who will do the work, check company and tax registration, and review previous FAT and commissioning records.

Is turnkey more expensive than buying machines myself?

The quote is usually higher, but it includes design, coordination and risk that you would otherwise carry yourself.

What should a turnkey contract guarantee?

Output, product quality and waste targets measured in an acceptance test, with payment tied to passing it.