Most failures come from doing it the other way round: buying machines first and looking for customers later. Equipment is usually only about 35–55% of the total project, so the building, power, permits, raw materials and working capital need as much planning as the line. This page sets out the order and links to our guides for specific products, from bakeries and bottled water to bricks, paint and recycling.

The order that works

StepWhat you decideWhy it comes here
1. ProductWhat you will make, for whom, in which packsEverything else follows from it
2. Market testBuyers, price, volumes, channelsProves the business before you spend on machines
3. NumbersCost per unit, capital, working capital, break-evenTells you the size of line you can afford and fill
4. RegistrationCompany, tax, employer registrationsNeeded to contract, import and employ
5. SiteZoning, power, water, effluent, accessThe line must fit the site and the site must allow the activity
6. ApprovalsProduct and premises rules for your sectorSome take months
7. LineSpecification, supplier, contract, factory acceptance testBought against a clear product and output
8. Installation and trialsInstallation, commissioning, test runs, trainingFirst saleable product
9. LaunchFirst orders, quality routines, maintenanceSteady production

Step 1: Choose the product

Start from what people already buy, in a market you can reach, where you can be competitive on cost, quality or delivery. Good first products often share some features: a steady local demand, raw materials available nearby, products that are bulky or perishable so imports are at a disadvantage, and a line size that matches a realistic first market. Our guide to which production line to start compares common options.

Step 2: Test the market

Before you spend on machines, find out:

  • Who will buy, by name: shops, wholesalers, contractors, institutions.
  • At what price, for which pack, with which payment terms.
  • How much, each week or month.
  • Against whom: the products they buy now and why they would switch.

Small trial batches, made by hand or by a contract manufacturer, are the best market test.

Step 3: Do the numbers

Work out:

  • Cost per unit: raw materials, packaging, energy, labour, maintenance, delivery.
  • Capital: equipment, building work, power connection, installation, vehicles.
  • Working capital: raw material stock and the time customers take to pay.
  • Break-even volume and how long it takes to reach it.

In most lines we see, equipment is about 35–55% of the project cost. Our guide to the cost of setting up a small factory breaks down the other blocks.

Step 4: Register the business

  • Company: register with CIPC.
  • Tax: income tax, and VAT once your turnover passes SARS's compulsory threshold, or voluntarily earlier, which lets you claim VAT on equipment.
  • Employer: PAYE, UIF and registration with the Compensation Fund once you employ people.
  • Customs: register as an importer with SARS if you will import equipment or raw materials.
  • Bank: a business account and, for imports, a trade finance contact.

Step 5: Find the site

The site often decides what is possible. Check:

  • Zoning: industrial or a use the municipality allows; change of use takes time.
  • Power: capacity for your machines' running and starting load; Eskom's standard tariffs rose 8.76% for 2026/27, and backup power for critical loads belongs in the plan.
  • Water: quantity and quality, municipal or borehole.
  • Effluent and waste: what you will discharge and how.
  • Building: floor strength, height, drainage, hygiene finishes for food, fire escapes.
  • Access: for trucks delivering raw materials and collecting products.

Step 6: Get the approvals your sector needs

SectorTypical approvals
Food and drinkCertificate of Acceptability under R638; labels; sector rules such as bottled water, juice or maize meal regulations
Cosmetics and detergentsLabels; disinfectant rules if you make germ-killing claims
Building materialsProduct standards such as SANS 1215 for blocks
RecyclingWaste management licence or norms, depending on activity and size
Feed and fertiliserRegistration under Act 36 of 1947
Any factoryZoning, building plans, fire, and machinery safety under the Driven Machinery Regulations, 2015

Start the slow approvals early, in parallel with the site and the line.

Step 7: Buy the line

Buy against a written specification: your product, packs, output per hour, raw materials, utilities and site. Compare quotes on the same scope, check the supplier, insist on a factory acceptance test before the balance is paid, and plan spare parts and training. Used machinery needs an ITAC import permit before it is shipped.

Step 8: Install, commission and train

Installation needs foundations, power, water, air and drainage ready on time. Commissioning should show the agreed output on your product, not a demonstration product. Train operators and maintenance staff before the supplier's engineers leave. Keep a punch list and close it.

Step 9: Launch and run

Start with the customers you tested. Keep quality records, plan preventive maintenance, and track output against the line's rating every shift. Most new lines take weeks or months to reach steady output.

Guides for specific products

How long it takes

Timelines vary by sector, but a typical first factory with an imported line runs roughly like this:

StageTypical duration
Product choice and market test1–3 months
Numbers, funding and registrations1–3 months, in parallel
Site, zoning and approvals2–6 months; longer if rezoning is needed
Line specification and contract1–2 months
Manufacture and factory acceptance test2–5 months
Shipping and clearing1–2 months
Installation, commissioning and training1–2 months

Running steps in parallel, especially approvals and line manufacture, is how most projects reach first production within a year.

Common mistakes

  • Buying machines before customers.
  • Choosing a site that cannot supply the power.
  • Leaving approvals until the line arrives.
  • No working capital for raw materials and slow payers.
  • Sizing the line for the market you hope for rather than the one you have.
  • No factory acceptance test.

Where CISH fits

Once the product, market and site are clear, CISH specifies a complete production line from audited factories in China against your product and output, ships and clears it, installs and commissions it with output demonstrated, and trains your team. We can also help earlier, by telling you which lines fit your budget and what each would cost landed.

Frequently asked questions

What is the first step to start a manufacturing business?

Choose a product and prove there are buyers at a price that covers your costs, before you buy equipment.

How much does it cost to start a factory in South Africa?

It depends on the product and scale. Equipment is usually about 35–55% of the total; the building, power, permits, raw materials and working capital make up the rest.

What registrations do I need to start manufacturing?

Company registration with CIPC, tax registrations with SARS, employer registrations once you hire, and importer registration if you import.

What permits does a factory need?

Correct zoning, building and fire approvals, machinery safety, and sector approvals such as a Certificate of Acceptability for food premises.

Can I import used machinery for my factory?

Yes, with an ITAC import permit obtained before shipment.

Does CISH help choose what to manufacture?

We can tell you which lines fit your budget and market, and what each would cost landed. The final product choice is yours.